Our Principal Engineer Ahmed Hammouri helped in delivering Third Reedy Lake Bypass Project as part of John Holland team during 2019 works. The project involved:
1- Establishment of a 750ML/day, 1.4km bypass channel;
2- Occupational Crossing;
3- New regulator and fish passage on the bypass channel;
4- Pump station; and
5- D1200 PN8 – 1.5km pumped pipeline connecting to the TO1/7 channel and landowner connections.

Project Value

$10m - $100m

Date

March 7, 2018

Category

Concrete, Earthworks, Pipelines, Pumping & Irrigation Systems